The Brief
Community-focused urban development is crucial to building a safe and sustainable neighbourhood. In phase one of this project, RVA worked with Halton Region to enhance Trafalgar Road in the Town of Oakville with urbanized improvements to accommodate different daily modes of transportation while ensuring everyday safety.
Project Overview
Improving Community Connectivity and Safety
The Trafalgar Road Improvements project was initiated by Halton Region to address the growing community transport needs and living standards. Located in the Town of Oakville, the project spans approximately 6.3 km, from Iroquois Shores Boulevard to William Halton Parkway. This project was divided into two phases, with phase one focusing on Leighland Avenue to North of Hays Boulevard in Oakville, Ontario.
What was the reason behind this project? There were rising concerns about pedestrians’ safety, the existing sidewalk located north of Leighland Avenue was too close to the road, and became uncomfortable for pedestrians, especially during the winter months. Due to lack of space, cyclists also avoided using the regional road as a cycling path.
RVA was retained by Halton Region for detailed design and contract administration of the road’s reconstruction, including widening improvements to accommodate projected increases in vehicular, cycling, and pedestrian activities. Bus bays and passenger platforms were improved, along with roadway and sidewalk illumination, and landscaping. Furthermore, due to aging infrastructure, a much-needed upgrade of storm sewers, wastewater service laterals, and watermains were carried out alongside the road reconstruction.
As the first project in Halton Region to feature a dedicated bridge specifically as a bike path and sidewalk, a people-centred approach was a hundred percent crucial. In a nutshell, the Trafalgar Road Improvements project was a holistic approach to ensure better living standards and safety for the community through sustainable measures.
The bike path was designed to curve toward intersections to make use of standard width crosswalks, with consideration of the phasing and implementation of a bike path network within the Town of Oakville. Channelized islands were removed at Sheridan College to eliminate two stage pedestrian crossings and shorten the distance of crossing in accordance with AODA standards. Traffic signals were designed for modified intersections with shortened crosswalks to accommodate active transportation users. Noise walls and landscaping were provided to ensure that the road corridor does not adversely affect the surrounding residents and environment.
To encourage usage and ensure safety, the pedestrian bridge is in an area visible to both vehicles and pedestrians. It is also directly across from Oakville’s Town Hall. For a more visually appealing structure, the project team opted for a concrete design for the bridge, instead of a prefabricated steel option, avoiding the need for unsightly steel cross bracing. This design choice creates a more attractive landmark for the community, especially given its prominent location.
Balancing Innovation, Environment, Safety, and Utility on Trafalgar Road
Like other similar projects that RVA has embarked on, delivering the Trafalgar Road improvements demanded meticulous environmental coordination, transportation planning, engineering design, and construction management. In collaboration with Conservation Halton, our team addressed the stormwater challenges by implementing an innovative treatment train approach to meet strict erosion control targets for the Oakville-Morrison Creek Watershed. This included super pipes using 1200 mm diameter pipes with orifice controls for peak flow management, infiltration galleries to reduce runoff volume, and advanced pollutant removal measures like oil-grit separators and catch basin shields as at-source pollutant removal devices. By using these proposed treatment train measures, we achieved an enhanced level of treatment (80% TSS removal) as required by the Ministry of Environment, Conservation and Parks (MECP).
As a main utility corridor for the Oakville area, the right-of-way’s dense network of utilities, including major hydro lines, telecom, gas, and a critical fibre line supporting the area’s public infrastructure required thorough and detailed coordination between all stakeholders to avoid issues during construction.
Essentially, RVA worked strategically with Halton Region to effectively minimize disruptions to ongoing traffic and everyday activities, especially since Trafalgar Road is a key connection to the Queen Elizabeth Way (QEW) which is a major highway. Key strategies used to minimize disruptions included real-time digital signage with Bluetooth technology to provide live travel updates, nighttime scheduling to effectively reduce impacts on traffic and businesses, and major works such as the Leighland Avenue watermain replacement were completed using trenchless methods
Building a Sustainable, Cleaner Future
The upgrades to Trafalgar Road were designed with the community in mind, ensuring accessibility, sustainability, and long-term benefits for everyone who lives, works, and travels in the area.
How was this achieved? Every signalized intersection within the project corridor was built to support future bicycle crossrides. Underground structures, from handwells to conduits, were designed and constructed with setbacks. With minor modifications in the future, bike signals can be implemented for a separated crossride through intersections. This allows bike signals to be implemented over the entire bike path network, instead of piece by piece – providing consistency for cyclists.
Furthermore, all bus shelters on the west side of Trafalgar Road were converted to solar panels, reducing electricity use and maintenance costs. This innovation contributes to a cleaner, more sustainable future while serving transit users daily.
The project team was able to provide stormwater management controls for Trafalgar Road that achieved all stormwater requirements set out by the conservation authority. These systems were designed to not only protect the community from potential flooding and water issues, but also support future development, and potentially provide a net benefit to the environment. Highlighting the project’s dedication to protecting natural ecosystems while fostering a greener, safer community.
In view of this, despite unforeseen challenges, including the COVID-19 pandemic, phase one of this project was completed in two years, ahead of schedule. This was made possible through careful planning, strong stakeholder collaboration, and innovative solutions, to ensure that Trafalgar Road continues to thrive as a transportation hub, that is both safe and sustainable.